Race to build offshore wind-fuelled US regional power grid heats up with PSEG-Orsted bid

New Jersey state utility in partnership with international sector pacesetter joins 12 other bidders in contest to construct multi-billion dollar transmission project

BL England generating station will be part of the offshore wind grid integration in New Jersey
BL England generating station will be part of the offshore wind grid integration in New JerseyFoto: Smallbones Public Domain
New Jersey utility PSEG and offshore wind developer Orsted are leading a pack of a dozen sector big-hitters which have submitted bids into mid-Atlantic regional transmission operator PJM’s New Jersey Offshore Wind Transmission Solicitation aimed at wiring together the state’s ambitious 7.5GW offshore wind target by 2035.

Along with PSEG-Orsted, which are bidding under Coastal Wind Link banner, the state has attracted 69 proposals from utilities and merchant transmission developers, including from grid developer Anbaric, as well as the US’ largest renewables operator, NextEra, and New York utility Con Edison.

The solicitation, initiated by the New Jersey Board of Public Utilities (BPU), is the first to incorporate PJM's new state agreement approach (SAA) transmission planning process that allows the grid operator to incorporate state public policy goals such as the development of offshore wind into its regional transmission expansion plan. Grid expansion plans typically target only reliability or market-efficiency criteria.

Coastal Wind Link’s suite of seven proposals meets all four objectives of PJM's solicitation, including upgrade of existing onshore transmission facilities, construction of new onshore and offshore infrastructure, and the creation of a grid at sea. The bids from Coastal Wind Link offer both 325kV and 400kV high voltage direct current (HVDC) export line options from offshore substations near the upcoming New York Bight lease area to as many as three landing sites some 90km away.

Several bids would leverage existing PSEG assets, such as the site of the 538MW Sewaren gas-fired combined cycle power plant currently operating in densely populated northern New Jersey.

“Sewaren wasn’t one of the points of interconnection identified by PJM, but we found that for very a very minimal amount of network upgrades, we'd be able to effectively use it as an HVDC conversion station,” Ray DePillo, head of PSEG’s offshore wind development unit, told Recharge.

New Jersey has taken the lead in in planned offshore wind transmission, addressing a key bottleneck in the US efforts at installed 30GW of offshore wind energy by 2030.

“Strategically planned and competitively procured transmission will... [minimise] transmission bottlenecks, reduce grid connection risks, minimise environmental and fisheries impacts, and increase competition between wind farm developers,” Janice Fuller, mid-Atlantic president for Anbaric Development, told the a US House of Representatives’ subcommittee last month.

Yesterday (Wednesday), Atlantic Power Transmission, a Blackstone portfolio company, announced its bid into the solicitation for up to 3.6GW of transmission capacity, expected to bring $1.3bn in economic value, and the company announced agreements with a consortium of labour unions to provide hundreds of union jobs.

As part of the SAA, the costs for the upgrades will be borne by New Jersey ratepayers, who currently pay $0.14/kWh in September versus $0.11/kWh national average. Coastal Wind Link’s options will cost between $2bn to $7bn.

PJM and the New Jersey BPU will jointly evaluate proposals by the second half of 2022, with the state retaining the right to move forward with any projects. The state could also mix-and-match proposals from several developers.

Transmission projects faces similar permitting and regulatory hurdles that all infrastructure projects confront as well as local opposition concerns, and constructability will be a major factor in the decision-making process.

PSEG has acquired right-of-way options for onshore transmission routes to its proposed collector stations and has conducted federal pre-permitting as well as community outreach. The utility claims a track record of successful transmission development in the state.

“We will be bringing a lot of the previous best practices that we've had in terms of hiring to the local communities and bringing economic development and support to those areas as well,” DePillo told Recharge.

New Jersey has already awarded nearly 4GW of offshore wind capacity, including 1.51GW to Atlantic Shores, an EDF Renewables-Shell New Energies joint venture, as well as 1.1GW Ocean Wind 1, owned by Orsted (75%) and PSEG (25%), and 1.15GW Ocean Wind 2, owned exclusively by Orsted.

New Jersey BPU announced a third-round auction for an additional 1.2GW of capacity beginning in Q2 2022 and will hold auctions every year until 2028 to meet the 2035 goal of 7.5GW.

(Copyright)
Published 2 December 2021, 18:54Updated 3 December 2021, 00:12
USOrstedPSEGAnbaricAtlantic Power Transmission