Port of Long Beach pitches 'largest offshore wind facility in US' for California 25GW goal
City-owned harbour is among nation’s busiest but is far south of lease areas and faces development challenges from military, ecological, and aviation concerns
The so-called Pier Wind proposal would see land reclaimed through dredging in the port’s outer harbour developed into “the largest facility specifically designed to accommodate the assembly of offshore wind turbines in the US”, the operator said.
The port, along with neighbouring Port of Los Angeles, is the busiest harbour complex in the US, serving as gateway to commerce with Asia. It is located 25 miles (40km) south of downtown Los Angeles.
The proposed terminal would not impact other port operations, added Cordero.
The Port of Long Beach’s plans “can be part of the multi-port strategy that California needs to manufacture, assemble and service floating offshore wind turbines and towers,” said Adam Stern, executive director, Offshore Wind California, a trade group of offshore wind developers and technology companies.
Long Beach faces several constraints, however, including distance from California’s wind energy areas (WEAs) in Morro Bay and Humboldt.
The port is more than 241 nautical miles (446km) from the closest leases at Morro Bay. Floating wind turbines towed from the port would need to pass through the heavily congested sea lanes of the Channel Islands while contending with potential height restrictions near Los Angeles International Airport (LAX) and Vandenburg Space Force Base.
Towing each completed unit “will take 60 hours without any delays, but realistically will probably take over a week,” said Alla Weinstein, founder of Washington state-based developer Trident Winds and a pioneer in West Coast floating wind.
California has the nation’s largest offshore wind ambitions, aiming for 2-5GW by 2030 towards 25GW by 2045.
The highly anticipated auction – among the first commercial scale floating wind tenders in the world – brought in some $750m for up-to 7GW of potential capacity, a lower sum than expected. Cheap lease prices are attributed in part to multiple hurdles that will need cleared for large scale development, chiefly lack of port capacity.
Ambition meets reality
The state has 11 deepwater ports including San Francisco and San Diego, but only the Port of Humboldt Bay located near the Humboldt WEA has been tipped for floating wind marshalling and installation.
Morro Bay, by contrast, has no floating wind-capable port in the vicinity, and with development along the state’s extensive coastline strictly regulated, building a new port will be arduous and time consuming.
The National Renewable Energy Laboratory (NREL) is working on a parallel study, with both expected to be released this year.