Massachusetts approves US offshore wind contracts despite Avangrid’s call for dismissal

Surging inflation and rising interest rates have converged to put low-priced projects in the pioneering state at risk

Avangrid Vineyard Wind O&M. Pedro Azagra, CEO of Avangrid.
Avangrid Vineyard Wind O&M. Pedro Azagra, CEO of Avangrid.Foto: Avangrid
The US state of Massachusetts greenlighted offshore wind power purchase agreements (PPAs) signed between developers and utilities despite Avangrid’s call for dismissal of its Commonwealth Wind project on deteriorating economics.

Massachusetts regulator the Department of Public Utilities (DPU) approved offtake contracts for the 1.2GW project under development by Iberdrola-backed Avangrid as well as Mayflower Wind’s 405MW array in an order released today (Friday).

“Avangrid is disappointed in the order issued by the DPU today,” said Craig Gilvarg, Avangrid spokesperson, maintaining the company position that the current PPAs violate Massachusetts law requiring offshore wind projects be financeable.

“Because of the impact of unprecedented global economic headwinds, including historic inflation, sharp increases in interest rates, and supply chain bottlenecks, the current PPAs do not allow the company to secure the significant financing needed to construct this critical project,” Gilvarg said. “The project cannot proceed under these contracts.”
Danielle Burney, deputy communications director for the state executive office of energy and environmental affairs, told Recharge that the regulator reviewed Avangrid’s request to dismiss the contracts, but “Avangrid did not provide evidence, and therefore, the DPU did not find grounds for dismissal.”

Commonwealth was selected in the state’s third tender with a bid of $72/MWh, while Mayflower – a joint venture (JV) of Shell and Ocean Winds – won its capacity with a $75/MWh offer.

The developers signed 20-year PPAs with three utilities, Eversource, National Grid, and Unitil, which were submitted for review to state officials to ensure they “meet the requirements of law and deliver reliable and clean energy at an affordable price”, according to DPU.

In October, however, both developers called for a pause in the review process to renegotiate PPA terms, which was rejected by the DPU.

Avangrid ultimately moved to dismiss the contracts earlier this month and have Commonwealth’s capacity applied to Massachusetts’ upcoming tender in the spring.

“The best path to move the project forward as expeditiously as possible is through Massachusetts’ forthcoming offshore wind solicitation this spring,” said Gilvarg.

In denying Commonwealth’s motion, DPU said that Commonwealth failed “to justify review of the PPAs” and “ordered that the PPAs between [the utilities] and Commonwealth Wind [and] Mayflower Wind are approved”.

Massachusetts has 3.2GW under contract, including the US’ first commercial scale offshore wind farm, the 800MW Vineyard Wind 1. The state is mandated to have 5.6GW under contract by 2027.

Gilvarg said that Avangrid “continues to review the DPU’s decision while assessing its legal options”.

Mayflower did not respond to requests for comment as of time of publication.

Future price impacts

Commonwealth is the first major US project to walk away from a signed PPA but might not be the last as global economic conditions continue to negatively impact long-term offshore wind PPAs.

“Offshore wind as a new a new industry is not immune to the impacts of global economic trends and certainly rising prices worldwide have had an impact,” said Josh Kaplowitz, head of trade group American Clean Power Association’s offshore wind unit.

Avangrid’s efforts to gain a higher PPA will give developers “food for thought going into upcoming state solicitations”, said Wood Mackenzie senior wind analyst Samantha Woodworth.

Several states are slated for offshore wind tenders next year, including New York, New Jersey and Massachusetts, and the industry will be watching for Commonwealth’s impact on future prices.

“Inflation and other cost considerations will start being included in bid prices, or perhaps there will be added contract language that would allow PPA renegotiation or re-bidding of a project for this kind of force majeure,” said Woodworth.
(Copyright)
Published 31 December 2022, 03:05Updated 15 October 2023, 11:08
AmericasUSMassachusettsAvangridMayflower Wind